Service focus: Installation, logistics, occupational safety
Initial situation
Installation of several kilometres of steel cord conveyor belt in a cross-border tunnel, including additional textile belts. The project was subject to strict regulatory requirements and complex site logistics.
Our solution
- Deployment of our mobile workshop truck to ensure on-site autonomy
- Precisely sequenced installation under tunnelling conditions
- Flexible adaptation to local health & safety regulations
Result & added value
- Completion close to schedule despite challenging framework conditions
- Seamless material flow thanks to clean handovers and fully documented installation work
Special aspects
Logistics and bureaucracy under control: from acoustic warning systems to access rules – all safety and regulatory requirements were coordinated and implemented from a single source.




Industry: Infrastructure / Mining
Duration: approx. 3 weeks
Service focus: Installation, logistics, occupational safety